Milestones
Year |
Milestone |
---|---|
2024 |
|
2023 | i) With the commissioning of Interregional Link: “765 kV D/C, Warora – Warangal (New) Transmission Line (665 ckm) implemented by M/s Adani Energy Solutions Limited Interregional capacity has increased by 4200 MW in Oct’ 2023. It is now 1,16,540 MW.
ii) Following important EHV lines have been commissioned: a. 765 kV D/C, Lakadia - Vadodara Transmission line (670 ckm) implemented by M/s Sterlite, commissioned in Jan’2023. b. 765 kV D/C, Hyderabad – Kurnool Transmission Line (335 ckm) implemented by M/s Adani Energy Solutions Limited commissioned in July’2023. c. 765 kV D/C, Warangal (New) – Hyderabad Transmission Line (268 ckm) implemented by M/s Adani Energy Solutions Limited in Sep’2023. d. 400 kV, 2xD/c, Bikaner-II PS – Khetri line (1102 ckm) implemented by PGCIL, commissioned in June’2023. e. 400 kV D/C, Warangal (New) – Chilakaluripeta Transmission Line (392 ckm) implemented by M/s Adani Energy Solutions Limited in Sep’2023. f. 400 kV D/C, Koppal PS- Narendra (New) Transmission Line (276 ckm) implemented by M/s ReNew Transmission Venture Private Limited in Oct’2023. g. 400 kV D/C Lower Subhansiri - Biswanath Chariyali line -II (371 ckm) under Part C of North East / Northern Western Interconnector -I Project in Dec’2023. Cabinet Committee on Economic Affairs (CCEA) approved the project “Green Energy Corridor (GEC) Phase-II – Inter-State Transmission System (ISTS) for 13 GW Renewable Energy Project in Ladakh”. The project is targeted to be set up by FY 2029-30 with total estimated cost of Rs. 20,773.70 crore and Central Financial Assistance (CFA) @ 40% of project cost i.e. Rs.8,309.48 crore for the project. POWERGRID has been assigned as an implementing agency for this project. |
2022 |
765KV, D/C, Dharamjaygarh Pool section B - Raigarh (Tamnar) Pool line (G-TTPL-TBCB) (137CKM) implemented by SGL, commissioned in Jun’22.
400KV, D/C, Jeerat (New) - Subhasgram (PM-JTL-TBCB) (214 CKM) implemented by PGCIL, commissioned in Aug’22.
All 13 REMs assigned to POWERGRID are now operational.
|
2021 |
|
2020 |
|
2019 |
|
2018 |
|
2017 |
|
2016 |
NER directly connected with NR. The longest 6000 MW HVDC line (±800 kV) from Bishwanath Chariali in NER to Agra in NR for dispersal of power from NER to NR/WR |
2014 |
The Southern Grid synchronously connected with rest of all-India grid in December, 2014 through S/C 765 kV Raichur- Solapur line |
2013 | The Southern Grid synchronously connected with rest of all-India grid in December, 2014 through S/C 765 kV Raichur- Solapur line |
2011 |
Implementation of Point-Of-Connection (PoC) based method for sharing transmission charges and losses all across the country. |
2010 |
Notification of POSOCO – as a separate entity for operation of RLDCs and NLDC |
2007 |
|
2006 |
Synchronous inter-connection of NR with ER-NER-WR system led to the formation of NEW grid (with commissioning of Muzaffarpur-Gorakhpur 400 kV D/C line, the Northern Region also got interconnected to this system making an upper India system having the NR-WR-ER-NER system |
2004 |
Open access in transmission |
2003 |
|
1999 |
Transmission planning re-oriented towards all-India System |
2000 |
Introduction of 765 kV transmission line (initially charged at 400 kV) |
1990 |
Introduction of HVDC bi-pole line |
1992 |
The Eastern Region and the North-Eastern Region were synchronously interconnected through the Birpara- Salakati 220 kV D/C transmission line |
1980-88 |
Growth of Regional Grid Systems as Associated Transmission System with Central Sector Generation |
1989 |
Development of HVDC back-to-back System |
1977 |
Introduction of 400 kV voltage level |
1965-73 |
Interconnection of State Grids to form Regional Grid Systems |
1964 |
Constitution of Regional Electricity Boards for integrated operation of grid at regional level |
1950-60 |
Growth of State Grids and introduction of 220 kV voltage level |
1948 |
Electricity (Supply) Act- 1948. The Act provided for establishment of the Central Electricity Authority (CEA) and the State Electricity Boards |